Client/Owner
Name: RTP Co.
Address: 1325 Adams Street, Portage, WI 53901
Project Cost
$2,404,070.50
Project Schedule
Start Date: 10/13/17
Completion: 10/13/18
Brief Overview
WC was constructed to install the process cooling which consisted of stainless steel piping distributed to eight fluid coolers and two 220 ton chillers. We also installed a PLC System to allow the plant manager control of the system
Key Aspects of Project
- 2-220 ton Chillers
- PLC System